Fishkill Commerce Center Sewer Connection and Aquifer Protection
Town of Fishkill
Summary
The developers of the Fishkill Commerce Center warehouse presented a major design change that replaces an on-site septic system with a 2,500-foot underground force main running beneath Interstate 84 into the Village of Fishkill.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 11, 2026.
Impact analysis
Private investment by the developer covering extensive utility extension and boring costs.
The developer and local watershed protection agencies by avoiding a large septic field.
None identified at this preliminary review stage.
Mentions & discussions (2)
Planning Board - Regular Meeting — June 11, 2026
The developers of the Fishkill Commerce Center warehouse project updated their plans to eliminate an on-site septic system, opting instead to directionally drill a force main 3,000 feet across Interstate 84 to connect to the Village of Fishkill's sewer system. Experts and board members discussed potential impacts on the town's critical aquifer overlay zone and water resources.
Planning Board - Regular Meeting — April 9, 2026
The developers of the Fishkill Commerce Center warehouse presented a major design change that replaces an on-site septic system with a 2,500-foot underground force main running beneath Interstate 84 into the Village of Fishkill.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Town of Fishkill
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.